LiveTrafik
RoadworksModerate

US 35 (Mile Point 120.15 - 119.71): Lane closed.

US 35: Between South St and IN 218.

...

Between South St and IN 218 (Walton). A lane is closed. Work on underground cables is in progress. Utility work is in progress. There is work on the shoulder. The shoulder is closed. Look out for flaggers. Until October 2, 2026 at about 5:00PM EDT. Comment: Permit-T211259-Frontier buried and aerial broadband fiber-The applicant proposes placing a total of 203’ cable in the right of way of US-35 by HDD boring and pulling FTR fiber cable within and 1946’ cable by over-lashing of aerial fiber onto the existing cable.-Location is between SR 218 and South St along US 35 in the town of Walton-Lane and Shoulder Restriction-No Detour.

ReportedSeptember 1, 2026 at 05:00 AM PDTOctober 2, 2026 at 02:00 PM PDT
Road
US 35
Source
INDOT
Coordinates
40.65803, -86.24117

Roadworks details

Direction
NOT_DIRECTIONAL
🚧 Roadworks
US 35 (Mile Point 120.15 - 119.71): Lane closed. | LiveTrafik